Meeting Critical Requirements
Material control and traceability are critical requirements of Level 1 valves. At Hunt Valve, we incorporate the controls and inspections required to maintain the material traceability back to the original mill heat.
Hunt Valve utilizes a segregated, controlled storage areas for both finished components and raw materials. The raw material and finished component storage areas are secured with restricted access. Raw material and finished machined components are segregated into three different areas depending on their required level of traceability: Military Non Level 1, Military Level 1 and Industrial. This separation prevents any commingling of raw materials or finished parts, ensuring superior product quality and integrity.
All materials are inspected before being received at Hunt Valve. Our precise receiving inspection process includes:
- Dimensional inspection
- Mercury-free inspection
- Alloy verification
- Material certification review
If any element is found to be in violation of our strict standards, then the material is rejected before being received into our facility.